EXECUTION STAGES OF BRIQUETERIE JEBAL EL OUEST PROJECT IN TUNISIA

The project for the construction of  Briqueterie Jebal El Ouest factory for the Poulina Group in Tunisia, aiming at the construction of state-of-the-art factory in terms of technology and meeting strict energy consumption requiremetns, is moving forward at a fast pace. Find below a report of the main execution stages of the project:

FIRST KILN CAR WITH FIRED WARE OUT OF THE KILN - MAY 2019

SETTING ON FIRST  KILN CAR - APRIL 2019

First kiln car loaded with ware to be fired and ready to enter the kiln.

KILN DRYING AND START OF LOAD TESTS - MARCH 2019

Drying of the kiln and start of tests with load.

DRYER TESTS - FEBRUARY 2019

Start of dryer tests and burners ignition.

NON-LOAD TEST AT THE LOADING AREA - DECEMBER 2018

Completion of mechanical and electrical assembly works and start of non-load tests at the loading area.

CIVIL WORKS COMPLETION AND START OF MACHINERY ASSEMBLY AT SITE- MAY 2018

Civil works have already been completed and machinery assembly works have  started at site.

KILN CIVIL WORKS-FEBRUARY 2018

Development of  civil works for the construction of the Gaudi sealed kilns.

MACHINE TESTING AT EQUIPCERAMIC WORKSHOP-OCTOBER 2017

All machines are subject to strict verification test at Equipceramic's workshop before being shipped to site.

DEVELOPMENT OF CIVIL WORKS-SEPTEMBER 2017

Start of civil works.

START OF FOUNDATIONS-AUGUST 2017

Development of the works for the foundations of the factory.

KICK-OFF OF THE WORKS  - JULY 2017

Equipceramic and Briqueterie Jebal El Ouest teams work together in the kick-off meeting to start  works on site.

BJO

Briqueterie Jebal El Ouest

 bjomap

Production: 1200 t/day hollow bricks.
Dryer: Barna dryer.
Kiln: Gaudí sealed kiln.
Location: Bou Mhel, Tunisia.